Thanks for joining the movement!

Thanks for joining the movement in our shared mission to a sustainable Aruba! The enthusiasm around the Solar Plan initiative has exceeded all expectations, which means that our sustainable future is now!

We’re committed to keeping you informed every step of the way.


Here’s what you can expect:

Step 1: Join the Movement – Done! Welcome aboard.

Step 2 (maximum 1–2 months): Permit Process
Within a month of signing, we’ll kick off the permit process. Our operations team will reach out shortly to get the preliminary approvals started. This step is key to ensuring a smooth path forward.

Step 3 (maximum 3 months): Installation Prep
Around the three-month mark (maximum), we’ll begin preparing for installation. Our team will send you a link to choose a convenient time for the installation. We’ll take care of everything, but someone will need to be present to grant us access to the property.

Step 4 (maximum 5–6 months): Final Approvals
This phase involves final approvals from Elmar and DTI. It can take a little time, but rest assured, we’ve got it covered. Importantly, billing only starts once the system receives final approval, not a moment sooner.

Step 5 (maximum 7 months): System Activation and Billing
Once the system is live, it will begin generating energy. Billing starts on the first day of the month following final approval. For example, if your system is approved on September 15, billing would begin on October 1, giving you 15 days of energy completely free!

We’re thrilled to be on this journey with you. If you have any questions in the meantime, feel free to reach out, we're here to help.

Oh and bonus, below a special video for you to show you our appreciation: